CBC Reports on Astaldi Lawsuit

Excerpt from our Facebook Page, June 8, 2018

Let’s not forget how insider info pointed towards the rush job, lack of tools and pressure from supervisors to complete..stories of multiple crews on the one site all trying to do diff jobs.

“A report commissioned by Nalcor Energy found that at least one of the following things happened:

-The shoring system was not designed properly;
-Wood integrity of the formwork was compromised;
-The shoring system was not installed correctly;
-The shoring system fabrication was inadequate.

That report, issued a year after the incident, also indicated a combination of those factors could have led to the collapse.”

Read CBC’s report June 8, 2018

Astaldi sues U.S. firm over 2016 Muskrat Falls concrete collapse

 

 

Hits: 46

Tags: , , , ,